Masjid Zakariya Phase 2 – Construction Update & Urgent Appeal

Masjid Zakariya Construction – Total Cost $4 million

Alhamdulillah, with your generous support, Masjid Zakariya Phase 2—a 28,000 sq. ft. expansion—has seen good progress since construction began in November 2024.

Achievements So Far

  1. Structural reinforcements completed (ceiling joists, beams)
  2. Framing and layouts of interior walls completed
  3. HVAC ducting installed
  4. Insulation installed
  5. Electrical work completed
  6. Fire sprinkler system installed
  7. Fire alarm system installed

A major milestone was achieved on September 3, 2025, when the City inspections for Mechanical, Electrical, Plumbing and Framing were officially passed.

Over the past year, our community has donated $1 million, allowing us to reach this stage. We currently have a balance of $1.2 million, which will now be used to complete:

  • New Prayer Area for Sisters
  • Women’s Activity Area
  • Youth Sports Facility
  • Multi-Purpose Events Center (to serve both masjid and community needs)
  • Classrooms for Darul Uloom & ILM Academy

Recent Construction Milestones

Date Construction Task
Dec 22nd, 2024 Adding Ceiling Joists to Support Beams
Dec 22nd, 2024 MZ Open House – Construction Updates presented followed by Q&A
Dec 9th, 2024 Gym Areas (Halls) closed for public
Nov 19, 2024 Layout for Walls